why_does_high_a_utilization_rate_make_it_impossible_to_create_good_estimates
Differences
This shows you the differences between two versions of the page.
Both sides previous revisionPrevious revisionNext revision | Previous revision | ||
why_does_high_a_utilization_rate_make_it_impossible_to_create_good_estimates [2018/12/03 19:36] – Added todi hpsamios | why_does_high_a_utilization_rate_make_it_impossible_to_create_good_estimates [2021/01/05 12:44] (current) – Completed first draft of page hans | ||
---|---|---|---|
Line 1: | Line 1: | ||
- | I ====== Why Does a High Utilization Rate Make It Impossible to Create Good Estimates? ====== | + | ====== Why Does a High Utilization Rate Make It Impossible to Create Good Estimates? ====== |
- | <WRAP todo> | + | Or "Why do we have to match capacity with demand |
- | Have a look at the following | + | People often wonder why we are so poor at estimating knowledge work. There are many reasons, but one effect that is often neglected is the effect of high utilization rates. Many product development organizations and IT shops pride themselves on their high utilization rate, thinking that the more busy people are the more we are getting from the dollars we spend on those people, and so the more efficient we will be. [[https:// |
+ | |||
+ | > What this means is that if you have full utilized people or Teams you will probably be seriously wrong with estimates you make. | ||
+ | |||
+ | To understand this impact, have a look at the following | ||
{{ image.jpeg? | {{ image.jpeg? | ||
- | As you can see, as you increase the utilization rate of people, the amount of time it takes to complete something on average increases, and after about 80% increases dramatically. If you are trying to estimate work and you have a high utilization rate, then which number would you use - the one represented at the lower end of the curve, or the one at the high. The difference is " | + | This a well known result for all kinds of queues of work, including knowledge work. The chart shows the effect of increasing average utilization on the average time it takes to get something done. As you can see at the beginning of the chart, as you increase utilization, |
+ | |||
+ | Now, instead of understanding the effect of utilization on time it takes to get things done, lets say we want to understand how long it will take to get something done. If we have reasonable utilization rates then we can make a pretty good guess at how long something will take, based on what has occurred in the past. | ||
+ | |||
+ | But if you are trying to estimate work and you have a high utilization rate, then which number would you use - the one represented at the lower end of the curve, or the one at the high. The difference is " | ||
+ | |||
+ | What this means is that before you can begin to expect reasonable estimates (discounting all the other things that could go " | ||
- | {{tag> | + | {{tag> |