what_is_the_basis_of_our_estimating_process
Differences
This shows you the differences between two versions of the page.
| Both sides previous revisionPrevious revisionNext revision | Previous revision | ||
| what_is_the_basis_of_our_estimating_process [2019/01/07 11:20] – Refactored to flow better hpsamios | what_is_the_basis_of_our_estimating_process [2020/11/02 10:49] (current) – Cleaned up for readability hans | ||
|---|---|---|---|
| Line 1: | Line 1: | ||
| ====== What is the Basis of Our Estimating Process? ====== | ====== What is the Basis of Our Estimating Process? ====== | ||
| - | The basis of this discussion | + | The basis of the estimating process |
| - | * We do relative size estimates (how big something is in relation to something else) estimates, not duration (how long something takes). | + | * We do relative size estimates (how big something is in relation to something else), not duration |
| - | * We use a team based approach to estimation such as planning poker or affinity (triangulation | + | * We use a team based approach to estimation such as planning poker or affinity (or triangulation) estimation |
| - | * We have the people doing the work doing the estimates | + | * We have the people |
| * We use the modified Fibonacci sequence (1, 2, 3, 5, 8, 13, 20, 40, 100) for estimating | * We use the modified Fibonacci sequence (1, 2, 3, 5, 8, 13, 20, 40, 100) for estimating | ||
| * All data we collect can and should be used to understand what and how we are doing so that we can get better. | * All data we collect can and should be used to understand what and how we are doing so that we can get better. | ||
| + | * The estimation process is refined. Estimations are revisited to see if they are accurate and precise enough. | ||
| - | It is worth delving into the notion of a relative size estimate for a moment. Most traditional estimates are based on duration, and that leads to a whole bunch of problems (see [[what_is_the_purpose_of_estimation|What is the Purpose of Estimation? | + | ===== Relative Estimates ===== |
| - | While the approach of using team based relative sized points is counter-intuitive at first, over time teams start to build up a a table of sizes in their heads: | + | >If two work items are the same size, should they always have the same estimate? |
| - | {{ : | + | It is worth delving into the notion of a relative size estimate for a moment. Most traditional estimates are based on duration ("it will take about 20 hours" |
| - | As a starting point a team might say " | + | One thing that often confuses people who are used to traditional task based estimates is that the resultant estimate is a Team's view of how big this item is. When we say the estimate is a " |
| - | <WRAP box>If a development team is equating some number | + | >In Agile the unit of execution |
| - | For more information on the basis of the process see [[https:// | + | For more information on the basis of the process see [[https:// |
| + | |||
| + | ====== Want to Know More? ====== | ||
| + | |||
| + | * [[where_did_this_estimation_approach_come_from|Where Did This Estimation Approach Come From?]] | ||
| {{tag> | {{tag> | ||
/home/hpsamios/hanssamios.com/dokuwiki/data/attic/what_is_the_basis_of_our_estimating_process.1546888840.txt.gz · Last modified: (external edit)
