 Or "When Should We Update Our Estimates?"​ Or "When Should We Update Our Estimates?"​
  
-Old habits dies hard. One of the interesting things that happens when we estimate using Team based Story Point estimates is that if, for whatever reason, we do the estimate and then follow it up with the work, and it turns out (typically) that there was a lot more work than originally estimated, then we will want to "​improve" ​the estimate ​by revising the data. Many people feel like they should update ​the estimate ​to improve the data now that they have improved knowledge.+Old habits dies hard. One of the interesting things that happens when we estimate using Team based Story Point estimates is that once the work is completeTeams want to update ​the estimate ​based on what they know now, and so “improve” ​the estimate.
  
 This is a mistake. ​ This is a mistake. ​
Line 26: Line 26:
 This kind of thinking applies the higher level structures (Epics / Features) as well.  This kind of thinking applies the higher level structures (Epics / Features) as well. 
  
-The basic rule is that you shouldn'​t update the estimate once you have "​started work" on it so you can look at all the data in your (Portfolio / Program) backlog with a single understanding of the status of the work effort - its a guess / no work. How you determine what it means to "start work" on an Epic or Feature will probably require some discussion since it may not be as clear cut.+The basic rule is that you shouldn'​t update the estimate once you have "​started work" on it so you can look at all the data in your (Portfolio / Program) backlog with a single understanding of the status of the work effort - its a guess / no work. How you determine what it means to "start work" on an Epic or Feature will probably require some discussion since it may not be as clear cut as the Story / Team example.
  
 ====== Want To Know More? ====== ====== Want To Know More? ======
  • /home/hpsamios/hanssamios.com/dokuwiki/data/pages/how_should_we_update_our_estimates.txt
  • Last modified: 2019/01/21 09:12
  • by hpsamios