   * The Train is constantly delivering value as represented by demonstrations of deliverable functionality. If we only get people to comment on value at the end of the PI this gives the false impression that value only is delivered at the end. We want to encourage discussions about delivering value continuously, not on some arbitrary time-box and so want to make sure everyone, especially senior people, know that value is always delivered.   * The Train is constantly delivering value as represented by demonstrations of deliverable functionality. If we only get people to comment on value at the end of the PI this gives the false impression that value only is delivered at the end. We want to encourage discussions about delivering value continuously, not on some arbitrary time-box and so want to make sure everyone, especially senior people, know that value is always delivered.
  
-A better approach is to have the business owner update the values as they are delivered. Typically as a result of a System Demonstration the business owner (or their proxies) will have seen the value provided. The team(s) are responsible for providing the link between the feature, the objectives and the work (stories) they have completed so there is a clear understanding of the value being provided.+A better approach is to have the business owner update the values as they are delivered. Typically as a result of a System Demonstration the business owner (or their proxies) will have seen the value provided. The team(s) are responsible for providing the link between the feature, the objectives and the work they have completed so there is a clear understanding of the value being provided.
  
 If the Business Owner attends the System Demonstration, we could get an updated value by saying to the Business Owner “ ... at PI Planning you said this was an 8. Now that you have seen it what do you think the value is?” If the Business Owner attends the System Demonstration, we could get an updated value by saying to the Business Owner “ ... at PI Planning you said this was an 8. Now that you have seen it what do you think the value is?”
Line 18: Line 18:
 It is OK for the Business Owner to say “this is now valued a 7 (i.e. lower value) than we original thought.” Sometimes this is because the business situation changed. Or it might be that after having seen the capability it’s just not as useful as it was. Whatever the case, we need this data to figure out how we can improve. Is there something we could have done to improve our communication? Is there something we could have done to understand the change in business environment? The key thing to understand is that there is no blame assignment here; the Team did not somehow fail. It is just data and we might be able to learn something from it. Metrics like the Predictability will fluctuate based changes in the Team’s ability to deliver and the changing business environment. We use this data in the Inspect and Adapt to help drive improvements. It is OK for the Business Owner to say “this is now valued a 7 (i.e. lower value) than we original thought.” Sometimes this is because the business situation changed. Or it might be that after having seen the capability it’s just not as useful as it was. Whatever the case, we need this data to figure out how we can improve. Is there something we could have done to improve our communication? Is there something we could have done to understand the change in business environment? The key thing to understand is that there is no blame assignment here; the Team did not somehow fail. It is just data and we might be able to learn something from it. Metrics like the Predictability will fluctuate based changes in the Team’s ability to deliver and the changing business environment. We use this data in the Inspect and Adapt to help drive improvements.
  
-Sometimes we find that Business Owners say they do not have the time to attend a System Demo or that they need to wait on something else before providing the value. My feeling is that the RTE should set up a working agreement with the Business Owner where in the event that the Business Owner is unable to provide a value, the RTE will simply assign the value that was originally given. Like most working agreements of this time, the other side of the agreement will be that the RTE will work hard to show the value to the Business Owner so they can provide feedback. In general this is a bit of an anti-pattern (we want Business Owners involved as much as possible), but especially as you are establishing Trains in a new organization, it something that you will often see.+Sometimes we find that Business Owners say they do not have the time to attend a System Demo or that they need to wait on something else before providing the value. My feeling is that the RTE should set up a working agreement with the Business Owner where in the event that the Business Owner is unable to provide a value, the RTE will simply assign the value that was originally given. Like most working agreements of this type, the other side of the agreement will be that the RTE will work hard to show the value to the Business Owner so they can provide feedback. In general this is a bit of an anti-pattern (we want Business Owners involved as much as possible), but especially as you are establishing Trains in a new organization, it something that you will often see.
  
 >> In summary, "How do we update the Business Value?" Incrementally, as the PI Objective is completed. >> In summary, "How do we update the Business Value?" Incrementally, as the PI Objective is completed.
  